The BIM productivity question
BIM coordination pays for itself on industrial projects through a specific mechanism — clash avoidance with mechanical, piping and electrical disciplines before fabrication starts. Everything else (visualisation, walkthroughs, marketing renders) is a secondary benefit.
What to scope into the BIM brief
- LOD targets — LOD 300 typically; LOD 400 only where prefabrication demands.
- Clash detection disciplines — structural, mechanical, piping, electrical, conveying systems.
- Tolerance bands — hard clashes vs. clearance violations vs. soft clashes.
- Federation cadence — weekly during detail design, fortnightly thereafter.
- Issue tracking platform — BIM 360 / Navisworks Manage with a numbered clash register.
- Deliverables — federated model, clash report, walkthrough video, take-off quantities.
What not to scope into BIM
- Cosmetic renders that don't drive a decision.
- Furniture, fittings or office-fitout LOD on industrial sheds.
- 4D sequencing on simple PEB jobs where it adds cost without adding speed.
MEC's BIM workflow
Coordinated 3D structural models built in Tekla or Revit, federated against client-supplied mechanical and piping models, with a numbered clash register tracked through to issue closure. Quantity take-offs are pulled directly from the model.